Today, we began construction of the deck. The design phase has been ongoing for about the last month.
We located the piers and dug half of them today. As you can see the soil is basically 100% red clay. I don't know if this is natural or if it was hauled in years ago when the subdivision was built. I suspect it is natural though. Native species don't seem to have any trouble thriving in it. As you can see in the pic there is a basil plant that is doing fine
No comments:
Post a Comment