Friday, June 20, 2014

Bathroom Demolition

Original bath

Demolishing the shower was not easy. The mortar bed that they installed in some places was over an inch thick. It was dry as a bone after 40 years. The tiler on this job did not get any call-backs I believe.

The amount of weight all of the mortar adds is incredible. The new materials will be a lot lighter.

There's at least one layer of wallpaper that's been painted over so all of the drywall has to go.

Behind the shower wall you can see the roof line of the first floor. (note the angled section). This wall gets really hot from the exterior. This will get another 2" of rigid foam insulation before the shower goes back in.

Sanitary waste and vent stack
I don't have the heart to smash the cast iron tub with a sledgehammer, so it stays.

That bundle of wires is heading down to the panel box. The new code doesn't allow any plumbing to be above any electrical.
Hot & cold water supplies









All the plumbing behind the walls is in good shape.